How do you calculate construction budget variance?

How residential builders should calculate and interpret construction budget variance after a project closes.

Direct answer

Construction budget variance is the difference between the budgeted cost and the actual cost. It can be calculated for the whole project or for each category. A useful variance analysis shows both dollars and percentage, separates original budget from revised budget, and explains which cost categories changed the project result most.

Key formula or definition

Formula
Variance = Actual cost − Budgeted cost. Variance percent = Variance ÷ Budgeted cost.

Why it matters

A small percentage overrun in a large category can matter more than a large percentage overrun in a small category.

The original budget, revised budget, and final actual can each tell a different story.

Example

If sitework was budgeted at $90,000 and finished at $132,000, the variance is $42,000. The variance percent is 46.7%.

That tells you where the project moved. It does not prove why it moved without the source records or project-team context.

Illustrative numbers only. Not Bivvit benchmark data.

What changes the result

  • Whether the comparison uses original budget or revised budget.
  • Whether change orders are shown separately or blended into actual cost.
  • Whether the final accounting report includes all invoices and closing adjustments.

How Bivvit handles it

Bivvit keeps original budget, revised budget, and final actual cost separate where the documents support it.

Bivvit ranks variances by their effect on profit and flags categories that repeat across multiple projects.

Related questions