Optional export example

See How Bivvit Can Be Shared.

Accounting tells you what happened. Bivvit tells you what it means.

Bivvit connects cost, timing, financing, sales, cash and profit so a completed project becomes more than a financial statement — it becomes a lesson for the next one.

A builder can use the findings privately or share an export with a business partner, accountant, investor, lender, or internal team.

Every figure on the following pages is illustrative data from a fictitious project.

Free. Send one project to start.

Private by default · Builder controlled

Your project information isn’t shared with lenders or other builders without your permission.

Page 1

Executive insights.

The project cost stack, the major metrics, and the three findings that mattered most — including how the carry problem moved from construction into sellout.

BivvitProject Insight Report

Executive Insights

Page 1 / 5
Project
Project Cedar (fictional example)
Product type
Townhomes (for sale)
Finished SF
9,840
Major metrics
Profit
$624,000
Margin
13.1%
Hard cost / SF
$267
Total cost / SF
$422
Construction duration
8.2 months
Total project duration
13.8 months
Equity invested
$1,180,000
Profit / equity invested
52.9%
Project cost stack
  • Land / acquisition$1,050,000
  • Hard costs$2,632,000
  • Soft costs$318,400
  • Financing & carry$148,600
Total project cost$4,149,000
Three things worth knowing
  1. 01

    Sitework Was the Biggest Miss

    +$38,400 over budget

    Sitework was the project's largest single cost overrun and, with no contingency carried in the original budget, the full amount flowed straight into project cost and profit.

  2. 02

    Stronger Pricing Carried the Project

    +$133,000 above the sales assumption

    Realized sales exceeded the original revenue assumption by $133,000, which more than covered $94,500 of combined cost overruns. Profit finished $38,500 ahead of budget on revenue, not on cost control.

  3. 03

    The Carry Problem Moved From Construction to Sellout

    21 days early to build · $15,200 of carry over budget

    Construction finished 21 days ahead of schedule, yet financing still finished above budget: $8,400 of interest over plan and $6,800 of extension fees that were never budgeted. The final closing landed 33 days after loan maturity, so the build was fast and the sellout wasn't fast enough to capture the financing benefit.

Supporting takeaway

Track construction carry and sales carry separately. A fast build only creates the full financial benefit if the project also exits on schedule.

Based on this project only.

Illustrative Data.

Page 2

Cost performance.

Land, hard costs, soft costs and cost per square foot against budget, detailed category variances, and a contingency analysis.

BivvitProject Insight Report

Cost Performance

Page 2 / 5
Project summary
Project type
Townhomes (for sale)
Units
8
Finished square footage
9,840 SF
Land / acquisition
$1,050,000
Total project cost
$4,149,000
Revenue
$4,773,000
Profit
$624,000
Margin
13.1%
Cost performance against budget
MeasureBudgetActualVariance
Land / acquisition$1,050,000$1,050,000—
Hard costs$2,567,000$2,632,000+$65,000
Soft costs$302,000$318,400+$16,400
Financing & carry$135,500$148,600+$13,100
Total project cost$4,054,500$4,149,000+$94,500
Hard cost / SF$261$267+$6
Total cost / SF$412$422+$10
Detailed hard cost categories
CategoryBudgetActualVarianceVar %$/SF
Sitework$214,000$252,400+$38,400+17.9%$25.65
Foundation$268,000$271,500+$3,500+1.3%$27.59
Framing$611,000$623,900+$12,900+2.1%$63.40
Roofing$96,000$94,200−$1,800−1.9%$9.57
Windows / doors$138,000$141,600+$3,600+2.6%$14.39
Exterior / siding$172,000$178,900+$6,900+4.0%$18.18
Plumbing$142,000$135,800−$6,200−4.4%$13.80
Electrical$128,000$141,200+$13,200+10.3%$14.35
HVAC$104,000$101,300−$2,700−2.6%$10.29
Insulation / drywall$186,000$183,400−$2,600−1.4%$18.64
Cabinets / millwork$149,000$146,700−$2,300−1.5%$14.91
Flooring / tile$121,000$118,900−$2,100−1.7%$12.08
Finish carpentry / paint$88,000$91,600+$3,600+4.1%$9.31
Appliances$46,000$45,200−$800−1.7%$4.59
Landscaping / exterior$62,000$68,700+$6,700+10.8%$6.98
Contingency$0$0——$0.00
Other$42,000$36,700−$5,300−12.6%$3.73
Total$2,567,000$2,632,000+$65,000+2.5%$267.48
Largest overruns
  • Sitework+$38,400
  • Electrical+$13,200
  • Framing+$12,900
Largest savings
  • Plumbing−$6,200
  • Other−$5,300
  • HVAC−$2,700
Bivvit observation

Most of the hard-cost variance sat in early site and structural work rather than in finish selections. Sitework, framing and electrical account for $64,500 of the $65,000 net hard-cost variance; every other category nets to $500. Finish and mechanical trades generally held. The records establish where the variance landed; whether it originated in estimating, site conditions or scope changes is a question for the project team.

Contingency
Original contingency budget
$0 — none carried
Contingency used
$0 — none available
Contingency remaining
$0
Contingency as % of hard costs
0.0% of hard costs
Hard-cost variance before contingency
+$65,000
Hard-cost variance after contingency
+$65,000
Bivvit observation

No contingency was carried in the original budget, so the full $65,000 hard-cost overrun flowed directly into project cost and reduced profit dollar for dollar. A 3% hard-cost contingency ($77,000) would have absorbed the entire variance without touching the profit line. The absence of contingency is itself a finding: on this project, every estimating miss became a margin miss.

Soft costs
CategoryBudgetActualVarianceVar %
Architecture / engineering$62,000$64,800+$2,800+4.5%
Permits / impact fees$86,500$90,600+$4,100+4.7%
Survey / geotech$14,000$18,300+$4,300+30.7%
Insurance$21,000$21,400+$400+1.9%
Utilities / connections$34,000$36,900+$2,900+8.5%
Legal / entity$9,500$8,800−$700−7.4%
Accounting / admin$12,000$11,600−$400−3.3%
Marketing / staging$18,000$21,200+$3,200+17.8%
Sales commission$39,000$40,100+$1,100+2.8%
Other$6,000$4,700−$1,300−21.7%
Total$302,000$318,400+$16,400+5.4%
Bivvit observation

Soft costs ran $16,400 over, led by permits and impact fees (+$4,100), geotech and survey (+$4,300) and marketing and staging (+$3,200). Geotech overruns appear alongside the sitework miss. That pairing is worth reviewing with the project team; the records do not establish the cause on their own.

Illustrative Data.

Page 3

Time, financing and cash.

Construction duration, sellout duration and total project duration alongside financing detail and the builder capital the project required.

BivvitProject Insight Report

Time, Financing & Cash

Page 3 / 5
Project dates
Land acquired / project start
Feb 3, 2025
Construction start
Apr 7, 2025
Substantial completion (planned)
Jan 2, 2026
Substantial completion (actual)
Dec 12, 2025
First unit listed
Dec 18, 2025
Construction loan maturity
Feb 15, 2026
Final unit closed
Mar 30, 2026
Time
DurationPlanActual
Construction durationApr 7, 2025 → Dec 12, 2025. Finished 21 days ahead of plan.8.9 months8.2 months
Sellout durationDec 12, 2025 → Mar 30, 2026. Final closing ran 33 days past loan maturity.2.5 months3.6 months
Total project durationFeb 3, 2025 → Mar 30, 2026. Land close through final closing.13.5 months13.8 months
Bivvit observation

Construction beat plan by 21 days, but sellout ran 33 days longer than assumed and the final closing landed after loan maturity. The build got faster; the project did not. Total project duration finished slightly longer than plan even though the construction schedule improved.

Financing & carry
CategoryBudgetActualVarianceVar %
Interest — construction period$83,000$78,900−$4,100−4.9%
Interest — after completion$21,000$33,500+$12,500+59.5%
Loan fees$21,000$21,000—0.0%
Extension fees$0$6,800+$6,800—
Property taxes / carry$8,500$7,200−$1,300−15.3%
Other financing costs$2,000$1,200−$800−40.0%
Total$135,500$148,600+$13,100+9.7%
Bivvit observation

Construction-period interest finished $4,100 under budget, alongside a build that finished 21 days early. Post-completion interest finished $12,500 over, and $6,800 of extension fees were recorded after the final closing landed 33 days past loan maturity. On this project the financing variance sits after completion rather than during construction.

Cash & capital
Equity invested

Total builder cash contributed across land close and construction draws.

$1,180,000
Peak cash exposure

Reached Dec 2025. No capital was returned before the first closing, so peak exposure equals total equity contributed.

$1,180,000
Capital duration

Feb 3, 2025 → Mar 30, 2026. Equity stayed committed until the final closing.

13.8 months
Cash returned at exit

Equity returned plus project profit.

$1,804,000
Profit / equity invested

Profit $624,000 ÷ equity invested $1,180,000. Unannualized.

52.9%
Equity multiple

$1,804,000 returned ÷ $1,180,000 invested.

1.53x
Bivvit observation

The project earned $624,000 on $1,180,000 of builder equity over 13.8 months — profit equal to 52.9% of invested equity, unannualized. The 3.6-month sellout accounts for about a quarter of that capital duration. Every month of sellout after completion affects return twice: carry goes up and the same profit is spread over a longer capital commitment.

Capital efficiency

How much cash did this project require, how long was it tied up, and what did it earn? On this project: $1,180,000, 13.8 months, $624,000.

Cash analysis requires equity contribution data. Where a project's equity, draw or closing detail is not provided, Bivvit reports "not enough data provided to calculate this metric" rather than assuming it.

Illustrative Data.

Page 4

Profitability.

Revenue, total project cost, margin, and a profit bridge that reconciles budgeted profit to actual profit line by line.

BivvitProject Insight Report

Profitability

Page 4 / 5
Expectation vs outcome
Original expectation
Budgeted revenue
$4,640,000
Budgeted cost
$4,054,500
Budgeted profit
$585,500
Budgeted margin
12.6%
Actual outcome
Actual revenue
$4,773,000
Actual cost
$4,149,000
Actual profit
$624,000
Actual margin
13.1%
Sales performance
MeasureBudgetActualVariance
Revenue$4,640,000$4,773,000+$133,000
Average price per unit$580,000$596,625+$16,625
Revenue / SF$472$485+$13
Sellout duration2.5 months3.6 months+1.1 months
Profit bridge
Budgeted profit$585,500
Positive contributions
  • Realized sales above the original revenue assumption+$133,000
  • Total positive+$133,000
Negative contributions
  • Sitework overrun−$38,400
  • Electrical overrun−$13,200
  • Framing overrun−$12,900
  • Other hard cost variances (net of savings)−$500
  • Soft cost variance, led by permits and geotech−$16,400
  • Financing & carry variance, including extension fees−$13,100
  • Total negative−$94,500
Actual profit$624,000

Bridge reconciles: $585,500 + +$133,000 −$94,500 = $624,000 (+$38,500 vs budget).

Bottom line

The project finished $38,500 ahead of its budgeted profit, and all of that came from revenue. Realized pricing beat the sales assumption by $133,000, which absorbed $94,500 of combined cost overruns — $65,000 hard, $16,400 soft and $13,100 of carry. Cost control did not improve this project's outcome; the market did. Repeat the pricing and the profit repeats. Repeat the sitework estimate and the next project keeps the overrun without the same guarantee of a stronger market.

Illustrative Data.

Page 5

What to take into the next project.

What to keep doing, what to watch, and where there is an opportunity to improve the economics of the next development.

BivvitProject Insight Report

What to Take Into the Next Project

Page 5 / 5
  • Keep doing

    Maintain the construction processes that delivered substantial completion 21 days early. Construction-period interest finished $4,100 under budget as a direct result, and mechanical and finish trades held to plan.

  • Watch

    Sitework assumptions and contingency. Sitework, framing and electrical account for $64,500 of the $65,000 hard-cost variance, and with no contingency in the budget the entire overrun landed on profit.

  • Opportunity

    Manage the project exit timeline as closely as the construction schedule. Sellout ran 1.1 months longer than planned and the final closing landed 33 days past loan maturity, which cost $6,800 in extension fees and $12,500 of post-completion interest.

  • Next project
    1. Complete sitework and geotech diligence before the construction budget is finalized, not after mobilization.
    2. Carry an explicit hard-cost contingency and report against it. A 3% line would have absorbed this project's entire overrun.
    3. Lock major electrical scope and pricing earlier in the schedule.
    4. Track construction carry and sales carry as separate lines so exit timing is visible on its own.
    5. Set the loan maturity date against a realistic sellout, then manage listing and closing dates against it weekly.

Your last project should make your next one better.

Illustrative Data.

Like What You See?

Send a project you already have and we'll apply the same analysis to your records.

The sample above shows an optional export from one fictional project. Your free Project Snapshot begins Bivvit’s private understanding of your completed-project history.

Free. Send one project to start.

Building the next one?

Building the Next One?

Send us the proposed budget for your next project and we'll compare the assumptions against your completed-project history and the records for the proposed project.

Check My Next Budget

Check your next budget